Demolition Project
Project ID: 2022-01 | Fiscal Year: 2023 | Funding Source: CDBG Grant & Local Match |
Description: The Town of Yemassee is pleased to announce the award of a Community Development Block Grant (CDBG) by the South Carolina Department of Commerce in the amount of $157,000 for the demolition of dilapidated and blighted properties in and around the Town. The grant will allow for the complete demolition of the structures to restore the property back to a conforming standard with our Community Ordinances.
Status:
Estimated Cost: $157,500.00 | Actual Cost: $11,600.00 | Actual End Date: N/A |
Estimated Start Date: 01/05/2023 | Actual Start Date: 01/05/2023 | Estimated End Date: 04/05/2023 |
On Budget | On Schedule | View Project Plans |
Phases:
Asbestos Testing: | Completed (September 2022) |
---|---|
Demolition Contract Execution: | Completed (January 2023) |
Demolition: | In Progress (March 2023) |
Closeout: | |
Remaining Phases: | 1 |
Project Team:
Role | Responsible Party |
---|---|
Project Engineer: | Terracon Consultants, Inc. |
Demolition Contractor: | Housley Demolition Co, Inc. |
Project Manager: | Lowcountry Council of Governments |
Town Staff Liason: | Matthew Garnes |