Castle Hall Sidewalk Extension
Project ID: 2022-01 | Fiscal Year: 2023 | Funding Source: General Fund |
Description: This project comprises the design and construction of new sidewalks, lighting and Stormwater Infrastructure on Castle Hall Road from the current sidewalk terminus at Wall St to the second entrance of the Beaufort Housing Authority Yemassee Heights development. The primary focus of this project is to create greater pedestrian connectivity from the downtown district to the public housing projects and improve citizen safety along the Castle Hall corridor.
Status:
Estimated Cost: $225,000.00 | Actual Cost: $25,000.00 | Actual End Date: N/A |
Estimated Start Date: 01/01/2023 | Actual Start Date: 12/14/2022 | Estimated End Date: N/A |
On Budget | On Schedule | View Project Plans |
Phases:
Pre-Design: | Completed (June 2022) |
---|---|
Design: | In Progress (December 2022) |
Construction: | |
Closeout: | |
Remaining Phases: | 3 |
Project Team:
Role | Responsible Party |
---|---|
Project Engineer: | |